Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Notice issued under section 64(2) of the Electricity Act 2003


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 

4. Fixed Charges

4.1 Capital Cost

The station comprises of 2 units of 210 MW each, the first unit was commissioned in September 1996 and the second unit in September 1997. The actual expenditure incurred for completion of the project was Rs. 1355.58 crores.

The details of funding the project cost are given in Table 16 below:

Table 16: Capital Cost – Funding

S.No.

Funding Source

Amount

(Rs. Crores)         

Phase 1: 2x210 MW

1

Equity Contribution by the erstwhile Government of Bihar

100.00

2

Bihar State Government Loan

608.90

3

Investment by BSEB

168.39

4

Loan from PFC

158.00

5

Interest during Construction.

320.29

6

Total for Phase 1

1355.58

The majority of the Phase 1 of the project was financed by the State Government while about Rs.158 crores (11.67 % of the funding) was financed by PFC. The entire loan obtained from PFC has been repaid completely along with interest. The outstanding loan is from State Government only. The Petitioner has requested the State Government to reduce the interest rate in view of the lower interest rates provided by banks. Response from the State Government is still awaited.

 The Petitioner is also planning to extend (Phase 2) the existing generating project, by adding three new units of 210 MW each, the capital cost of which for the FY 2007-08 is estimated to be Rs.354 crores. This is the Phase 2 of the generating project which will financed by a mix of debt in the form of funds from PFC and equity in the form of share capital contribution from Government of Jharkhand. It is expected to procure about Rs.284 crores from PFC and the remaining from the Government of Jharkhand.

4.2 Elements of Fixed Costs

The fixed costs include:

·        Interest on Loan

·        Depreciation

·        O&M Costs

·        Interest on Working Capital

·        Return on Equity

·        Tax on Income

The details are submitted below for consideration of Honourable Commission

4.3 Interest on Loan

The loan outstanding as on 31.03.2007 is Rs.665.9 crores. As per the terms and conditions the State Government loan is repayable in 15 equal installments. But the Petitioner could not meet the repayment obligation due to insufficient funds on account of non-payment of electricity charges by the Jharkhand State Electricity Board (JSEB).

Table 17: Loan Outstanding and Interest Charges (Rs.Crores)

 

 

S.No

 

 

Name of the Institution

Balance at the beginning of the year

Loan received during the year

Repayment During the year

Balance O/S at the end of the year

Rate of Interest

%

Interest for the year

 

2003-04

 

 

 

 

 

 

1

Bihar Govt.  Loan

608.90

-

-

608.90

13

79.16

 

Jharkhand Govt. Loan

30.00

-

-

30.00

13.25

3.98

 

Total 2003-04

638.90

-

-

638.90

 

83.14

 

2004-05

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

-

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

-

-

30.00

13.25

3.98

 

Total 2004-05

638.90

-

-

638.90

 

83.14

 

2005-06

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

-

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

19.00

-

49.00

13.25

6.49

 

Total 2005-06

638.90

19.00

-

657.90

 

85.65

 

2006-07

 

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

49.00

8.00

-

57.00

13.25

7.55

 

Total 2006-07

657.90

8.00

-

665.90

 

86.71

 

The Petitioner received Rs.8 crores from the Government of Jharkhand towards construction of MGR system in 2006-07. The total loan outstanding as on 31.03.2007 is therefore Rs.665.9 crores and interest payable on loan is Rs. 86.71 crores. The Petitioner’s inability to repay loan is due to non-recovery of dues from JSEB. Therefore the Petitioner requests the Honourable Commission to approve the interest charges for 2007-08.

Table 18: Loan Outstanding and Interest Charges for FY’07 (Rs.Crores)

 

 

S.No

 

 

Name of the Institution

Balance at the beginning of the year

Loan received during the year

Repayment During the year

Balance O/S at the end of the year

Rate of Interest

%

Interest for the year

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

57.00

-

-

57.00

13.25

7.55

 

Total 2007-08

657.90

-

-

665.90

 

86.71


4.4 Depreciation

The Petitioner has calculated the depreciation on its fixed assets on historical capital cost of the asset. Depreciation is calculated annually as per the straight line method as per rates of depreciation prescribed in the schedule attached at Appendix-II of the JSERC (Terms and Conditions for Determination of Thermal Generation Tariff) Regulations, 2004, and depreciation cost has been arrived at accordingly

Table 19: Depreciation (Rs. Lakhs)

S.No

Asset Classification

Asset value at the beginning of 2006-07

Rate of depreciation (%)

Depreciation

Amount (Rs.Cr.)

1

Land

3864.76

 

 

                Buildings

 

 

 

1

Factory Buildings

4210.34

3.6

151.57

2

Residential Buildings

2262.59

1.8