|
4.
Fixed Charges
The station comprises of 2 units of 210 MW
each, the first unit was commissioned in September 1996 and the
second unit in September 1997. The actual expenditure incurred
for completion of the project was Rs. 1355.58 crores.
The details of funding the project cost are
given in Table 16 below:
Table 16:
Capital Cost – Funding
|
S.No. |
Funding Source |
Amount
(Rs.
Crores) |
|
Phase 1: 2x210 MW |
|
1 |
Equity Contribution by the erstwhile Government of Bihar |
100.00 |
|
2 |
Bihar State Government Loan |
608.90 |
|
3 |
Investment by BSEB |
168.39 |
|
4 |
Loan from PFC |
158.00 |
|
5 |
Interest during Construction. |
320.29 |
|
6 |
Total for Phase 1 |
1355.58 |
The majority of the Phase 1 of the project was
financed by the State Government while about Rs.158 crores
(11.67 % of the funding) was financed by PFC. The entire loan
obtained from PFC has been repaid completely along with
interest. The outstanding loan is from State Government only.
The Petitioner has requested the State Government to reduce the
interest rate in view of the lower interest rates provided by
banks. Response from the State Government is still awaited.
The
Petitioner is also planning to extend (Phase 2) the existing
generating project, by adding three new units of 210 MW each,
the capital cost of which for the FY 2007-08 is estimated to be
Rs.354 crores. This is the Phase 2 of the generating project
which will financed by a mix of debt in the form of funds from
PFC and equity in the form of share capital contribution from
Government of Jharkhand. It is expected to procure about Rs.284
crores from PFC and the remaining from the Government of
Jharkhand.
The fixed costs include:
·
Interest on Loan
·
Depreciation
·
O&M Costs
·
Interest on Working Capital
·
Return on Equity
·
Tax on Income
The details are submitted below for
consideration of Honourable Commission
The loan outstanding as
on 31.03.2007 is Rs.665.9 crores. As per the terms and
conditions the State Government loan is repayable in 15 equal
installments. But the Petitioner could not meet the repayment
obligation due to insufficient funds on account of non-payment
of electricity charges by the Jharkhand State Electricity Board
(JSEB).
Table 17:
Loan Outstanding and Interest Charges (Rs.Crores)
|
S.No |
Name of the Institution |
Balance at the beginning of the year |
Loan received during the year |
Repayment During the year |
Balance O/S at the end of the year |
Rate of Interest
% |
Interest for the year |
|
|
2003-04 |
|
|
|
|
|
|
|
1 |
Bihar
Govt. Loan |
608.90 |
- |
- |
608.90 |
13 |
79.16 |
|
|
Jharkhand Govt. Loan |
30.00 |
- |
- |
30.00 |
13.25 |
3.98 |
|
|
Total 2003-04 |
638.90 |
- |
- |
638.90 |
|
83.14 |
|
|
2004-05 |
|
|
|
|
|
|
|
1 |
Bihar
Govt. Loan |
608.90 |
- |
- |
608.90 |
13 |
79.16 |
|
2 |
Jharkhand Govt. Loan |
30.00 |
- |
- |
30.00 |
13.25 |
3.98 |
|
|
Total
2004-05 |
638.90 |
- |
- |
638.90 |
|
83.14 |
|
|
2005-06 |
|
|
|
|
|
|
|
1 |
Bihar
Govt. Loan |
608.90 |
- |
- |
608.90 |
13 |
79.16 |
|
2 |
Jharkhand Govt. Loan |
30.00 |
19.00 |
- |
49.00 |
13.25 |
6.49 |
|
|
Total
2005-06 |
638.90 |
19.00 |
- |
657.90 |
|
85.65 |
|
|
2006-07 |
|
|
|
|
|
|
|
1 |
Bihar
Govt. Loan |
608.90 |
|
- |
608.90 |
13 |
79.16 |
|
2 |
Jharkhand Govt. Loan |
49.00 |
8.00 |
- |
57.00 |
13.25 |
7.55 |
|
|
Total
2006-07 |
657.90 |
8.00 |
- |
665.90 |
|
86.71 |
The Petitioner received Rs.8 crores from the
Government of Jharkhand towards construction of MGR system in
2006-07. The total loan outstanding as on 31.03.2007 is
therefore Rs.665.9 crores and interest payable on loan is Rs.
86.71 crores. The Petitioner’s inability to repay loan is due to
non-recovery of dues from JSEB. Therefore the Petitioner
requests the Honourable Commission to approve the interest
charges for 2007-08.
Table 18:
Loan Outstanding and Interest Charges for FY’07 (Rs.Crores)
|
S.No |
Name of
the Institution |
Balance
at the beginning of the year |
Loan
received during the year |
Repayment During the year |
Balance
O/S at the end of the year |
Rate of
Interest
% |
Interest
for the year |
|
1 |
Bihar
Govt. Loan |
608.90 |
|
- |
608.90 |
13 |
79.16 |
|
2 |
Jharkhand Govt. Loan |
57.00 |
- |
- |
57.00 |
13.25 |
7.55 |
|
|
Total
2007-08 |
657.90 |
- |
- |
665.90 |
|
86.71 |
The Petitioner
has calculated the depreciation on its fixed assets on
historical capital cost of the asset. Depreciation is calculated
annually as per the straight line method as per rates of
depreciation prescribed in the schedule attached at Appendix-II
of the JSERC (Terms and Conditions for Determination of Thermal
Generation Tariff) Regulations, 2004, and depreciation cost has
been arrived at accordingly
Table 19:
Depreciation (Rs. Lakhs)
|
S.No |
Asset Classification |
Asset value at the beginning of 2006-07 |
Rate of depreciation (%) |
Depreciation
Amount (Rs.Cr.) |
|
1 |
Land |
3864.76 |
|
|
|
Buildings |
|
|
|
|
1 |
Factory Buildings |
4210.34 |
3.6 |
151.57 |
|
2 |
Residential Buildings |
2262.59 |
1.8 |
40.73 |
|
3 |
Non Residential Buildings |
1709.31 |
1.8 |
30.77 |
|
Roads |
|
|
|
|
1 |
Pucca Roads |
1728.20 |
1.8 |
31.11 |
|
2 |
Boundary Wall & Others |
267.78 |
1.8 |
4.82 |
|
Plant and Machinery |
|
|
|
|
1 |
Plant &
Machinery |
104244.61 |
3.6 |
3752.81 |
|
2 |
D.G. Set |
216.16 |
6.0 |
12.97 |
|
3 |
Refrigeration |
2.41 |
6.0 |
0.14 |
|
4 |
Internal
Wiring |
0.11 |
6.0 |
- |
|
5 |
Overhead
line |
4295.14 |
3.6 |
154.62 |
|
6 |
Hydraulic works |
7956.24 |
1.8 |
143.21 |
|
7 |
Tools
and Tackles |
26.42 |
3.6 |
0.95 |
|
8 |
Miscellaneous Equipment |
61.54 |
6.0 |
3.69 |
|
9 |
Air
Conditioners |
31.57 |
18.0 |
5.68 |
|
10 |
Dozers |
282.25 |
18.0 |
50.81 |
|
11 |
Computers |
53.40 |
6.0 |
3.20 |
|
12 |
Furniture and Fixtures* |
35.77 |
6.0 |
0.18 |
|
13 |
Office
equipment* |
22.27 |
6.0 |
0.77 |
|
14 |
Vehicles
* |
16.60 |
18.0 |
- |
|
Total |
130917.39 |
|
4388.05 |
*
Depreciation applied only to newly purchased assets
As per the JSERC regulations, the residual
life of an asset is considered as 10% and depreciation is
allowed upto a maximum of 90% of the historical capital cost of
the asset. Therefore, depreciation is not calculated on the
assets where the cumulative depreciation has reached 90% of the
historical cost of such assets. It is requested that the
Honourable Commission may kindly approve the depreciation at Rs.
43.88 crores for the year 2007-08.
4.5 Operation and Maintenance (O&M)
Expenses
The O&M
expenses include expenditure incurred in the operation and
maintenance of the generating station, including employee cost,
repairs and maintenance, consumption of stores and spares, water
charges, ash disposal, pollution control cess, insurance and
other administrative and general expenses of the Petitioner
corporate office at Ranchi. The maintenance expenditure has
increased substantially due to the age of the plant and numerous
outages experienced. In the previous tariff order for FY 2005-06
the Honourable Commission had approved the normative O&M
expenses as per the JSERC (Terms and Conditions for
Determination of Thermal Generation Tariff) Regulations,
2004 for
plants set prior to 01.04.2004 that is 2.5% of the capital cost
escalated at 6% per annum from the year of commissioning. The
actual O&M expenditure for FY 2006-07 is estimated at Rs.86.26
crores. Using the normative approach, the O&M expenditure for
the year 2007-08 will come to only Rs.65.36 whereas
due to major breakdown maintenance and replacement
expenditure in Unit I due to tripping of its turbine resulting
in severe damage of blades, the Petitioner has projected an O&M
expenditure of Rs.142.40 crores out of which approximately
Rs.25-30 crores would be utilized in overhauling and repair and
maintenance of Unit I. Unit I is
expected to be under maintenance during FY 2007-08 since major
works would be required to be undertaken. The Petitioner
therefore requests the Honourable Commission to take
consideration of the unit breakdown and accordingly make
provision for O&M expenditure of Rs.142.40 crores for 2007-08.
Table 20: Proposed O&M Expenses
|
Year |
O&M Expenses
(Rs. Crores)
|
|
2007-08 |
142.40 |
The major components of the O&M expenses have
been explained below:
a)
Employee cost:
The actual
employee cost for FY 2006-07 was Rs.23.96 crores and for FY
2005-06 was Rs. 16.82 crores. The employee cost increases
continuously on account of inflation, increment in salaries and
wages, honorarium/incentives and increased demand for trained
manpower on account of increased development in infrastructure
sectors. For the year 2007-08 the employee cost is proposed at
Rs. 27.90 crores.
b)
Repairs and Maintenance (R&M):
The Petitioner
has to carry out regular repairs and maintenance of its
generating plant to ensure maximum generation by optimum
utilization of generating assets. The Petitioner undertakes
preventive maintenance activities for all critical assets in
addition to breakdown maintenance. The R&M expenses have been
projected considering the past trends and anticipated repairs
and maintenance. TVNL proposed Rs.2 crores for the FY 2005-06 as
the R&M costs while the actual R&M cost was more than Rs.7.7
crores largely due to the R&M of P.H.Area (civil). The actual
R&M costs in the year 2006-07 are estimated to be around Rs.3.11
crores on account of civil works in the non-residential
buildings and power house road and drains. The budget estimate
of the Petitioner for FY 2007-08 is Rs.1.73 crores. Other
maintenance expenditure like preventive and general maintenance
and store incidentals accounted for about Rs.17.75 crores in FY
2006-07 and are projected to be Rs.22.80 crores in FY 2007-08.
The Petitioner therefore requests the Honourable Commission to
approve Rs.24.54 crores inclusive of R&M expenditure and other
maintenance expenditures to keep its plant running since Unit I
of the plant is undergoing major overhauling
c) Administrative and General (A&G) Expenses:
A&G expenditure represents cost of general administration such
as rent, rates, taxes, legal expenses, professional fees,
conveyance and traveling expenses, printing and stationery, bank
charges, etc. The Petitioner had proposed an 8% increase in A&G
expenses in FY 2005-06 over the expenses of 2004-05 while the
actual growth was about 23.6%. In FY 2006-07 the A&G expenses
were estimated to be Rs. Rs.7.31 crores against Rs.7.51 crores
in FY 2005-06. The Petitioner proposes Rs.8.57 crores as A&G
expenses for the year 2007-08.
d) Capital Maintenance:
The Petitioner had incurred Rs. 86.82 crores towards capital
maintenance during the last 5 years period, that is 2002-03 to
2006-07, including towards spares.
These charges are being treated as deferred revenue expenses and
proposed to be charged to revenue account in 5 annual
installments. The year wise details of capital maintenance
expenses and the amounts proposed to be charged to revenue
account are detailed in the table below:
Table 21:
Year wise Capital Maintenance Expenditure (Rs. Lakhs)
|
Year |
Amount |
Proposed to be charged to Revenue in 5 annual installments |
|
|
|
2002-03 |
2003-04 |
2004-05 |
2005-06 |
2006-07 |
2007-08 |
|
2002-03 |
886.45 |
177.29 |
177.29 |
177.29 |
177.29 |
177.29 |
- |
|
2003-04 |
45.46 |
- |
9.09 |
9.09 |
9.09 |
9.09 |
9.09 |
|
2004-05 |
1209.48 |
- |
- |
241.90 |
241.90 |
241.90 |
241.90 |
|
2005-06 |
3267.00 |
- |
- |
- |
653.40 |
653.40 |
653.40 |
|
2006-07 |
2856.29 |
- |
- |
- |
- |
571.26 |
571.26 |
|
2007-08 |
5519.20 |
- |
- |
- |
- |
- |
1103.84 |
|
Total |
|
177.29 |
186.39 |
428.28 |
1081.68 |
1652.94 |
2579.49 |
The amount proposed to be charged
during 2007-08 is Rs.25.79 crores.
e) Ash Disposal:
Huge quantities of ash are piled up at the project site. TVNL
has incurred an estimated cost of Rs.5.59 crores towards
disposal of ash during the year 2006-07. For the year 2007-08
the Petitioner has projected expenditure of Rs.8 crores for
disposal of ash from ash ponds, as it is essential to dispose
off the piled up ash.
f) Interest on Working Capital: In
accordance with clause (v) of Regulation 21 of the JSERC (Terms
and Conditions for Determination of Thermal Generation Tariff)
Regulations, 2004, working capital in case of coal based fired
generation stations shall cover:
·
Cost of coal for 1˝ months
for pithead generating stations and 2 months for non-pithead
generating stations, corresponding to the target availability
·
One month stock of secondary
fuel oil
·
O&M expenses for 1 month
·
Maintenance spares @ 1% of
plant and equipment cost as on 01.04.2004 or the date of
commercial operation, whichever is later; and
·
Receivables equivalent to 2
months of fixed and variable charges for sale of electricity
calculated on target availability
As per the regulations, the rate of interest
on working capital shall be on a normative basis and shall be
equal to the short-term Prime Lending Rate of State Bank of
India as on 1st April of the year for which the tariff is
determined.
The
interest on working capital worked out to Rs.16.87 crores for
the year 2006-07 and it is estimated at Rs.15.19 crores for the
year 2007-08 as detailed in the Table 22 below:
Table 22:
Interest on Working Capital (Rs. Lakhs)
|
S.No |
Particulars |
2006-07
Actual |
2007-08
Estimate |
|
1 |
Cost of
Coal for 1˝ months |
2831.18 |
1819.64 |
|
2 |
Secondary Fuel Oil for 1 month |
145.41 |
98.96 |
|
3 |
Operation & Maintenance Expenses for 1 month |
718.84 |
1186.70 |
|
4 |
Maintenance Spares @ 1% of Plant and Equipment |
1187.72 |
1192.21 |
|
5 |
Receivables Equivalent to 2 Months of Fixed and Variable
Charges |
8615.98 |
7852.66 |
|
6 |
Total
Working Capital |
13499.13 |
12150.17 |
|
7 |
Interest
on Working Capital @ 12.5% |
1687.39 |
1518.77 |
The capital
cost of the TTPS (Phase I) comprising 2 units of 210MW each is
Rs.1355.58 crores and the equity is only Rs.100 crores much less
than the normative debt-equity ratio of 70:30 for the purpose of
determination of tariff. The Petitioner has submitted a proposal
to the State Government to raise the present equity of Rs.100
crores to Rs.1100
crores by converting the outstanding loan of
Rs.608.90 crores and part of the accumulated interest of
Rs.949.52 crores into equity. However no decision has been
communicated by the Government to the Petitioner till now.
Petitioner shall intimate the Honourable
Commission when such a decision is communicated by the State
Government to the Petitioner. For now the Petitioner in
accordance with Honourable Commission’s decision in Tariff Order
for FY 2005-06, seeks return on equity of Rs.14 crores at a rate
of return of 14% on equity for FY 2007-08.
Table 23:
Return on Equity (Rs.Crores)
|
Particular |
Proposed for 2007-08 (Rs.Crores) |
|
Equity |
100.00 |
|
Return on
Equity |
14.00 |
There is no assessable income for Income tax
purpose and hence no tax on income is proposed for the year
2007-08.
The fixed costs for the year 2007-08
are summarized below:
Table
24: Summary of Fixed Costs (Rs.Crores)
|
Particular |
Proposed for 2007-08 |
|
Interest on Loan |
86.71 |
|
Depreciation |
43.88 |
|
O&M Expenses |
142.40 |
|
Interest on Working Capital |
15.19 |
|
Return on Equity |
14.00 |
|
Income Tax |
- |
|
Total |
302.18 |
The proposed fixed charges of Rs.302.18 crores
and expected generation of 1679 MUs would result in a fixed
tariff charge of Rs.1.80/kWh. The Petitioner requests the
Honourable Commission to kindly approve this.
|