Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Notice issued under section 64(2) of the Electricity Act 2003


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 
1. Executive Summary

The Petitioner owns and operates an installed power generation capacity of 420 MW with two units of 210 MW each.  Historically the generating units have been operating at much below their potential because of transmission constraints and frequent tripping of transmission lines. In addition JSEB has not been in a position to consume the power generated when both the units operate and the station is asked to back down. However, in 2006-07, the plant has shown an impressive performance that can be attributed to both the units being able to dispatch simultaneously.

Table 1 provides the performance of the generating units during the period 2000-2007.

Table 1: Generation Performance (MU)

Year

Generation (MUs)

Total

Station PLF (%)

Auxiliary Consumption

(%)

Unit –I

Unit-II

2000-01

741

589

1330

36.11

16.09

2001-02

305

851

1156

31.39

15.79

2002-03

185

1183

1368

37.18

15.58

2003-04

616

731

1248

36.62

16.00

2004-05

1326

-

1326

36.04

17.60

2005-06

1240

289

1529

41.56

14.23

2006-07

1412

1303

2715

73.80

12.04

Based on last year’s performance the Petitioner has projected the following for the FY 2007-08:

Table 2: Projected Generation Parameters for FY’07

Year

Generation (MU)

PLF (%)

Auxiliary Consumption (%)

Heat Rate (kCal/kWh)

Specific Coal Consumption (kCal/kg)

Specific Oil Consumption (kCal/kg)

2007-08

1679

45.6

12.00

2821

0.656

2.31

However, Unit I of plant recently suffered a major breakdown due to sudden load throw-off resulting in severe damage of all the moving and guide blades of the LP turbines and it is expected to be back in operation only in FY 2008-09. This has resulted in an increase in fixed charges for the Petitioner per unit of generation.

The fixed costs projected for the year 2007-08 are summarized below:

Table 3: Summary of Fixed Costs (Rs.Crores)

 

Proposed for 2007-08

Interest on Loan

86.71

Depreciation

43.88

O&M Expenses

142.40

Interest on Working Capital

15.19

Return on Equity

14.00

Income Tax

-

Total

302.18

The cost of coal is billed by Central Coalfields Limited (CCL) at Rs.1097.89/MT and the transportation cost by road is Rs.160.85/MT. The delivered cost of coal at the thermal station was Rs.1258.73/MT during the FY 2006-07. Assuming a modest 5% increase in the cost of coal and transport the estimated cost per MT is considered at Rs.1321.67/MT for the year 2007-08.

Table 4: Summary of Variable Costs (Rs.Crores)

S.No

Item

Unit

2006-07 (Actual)

2007-08 (Proposed)

1

Coal Cost per Unit

Rs./kWh

0.948

0.995

 

Oil Cost per Unit

Rs./kWh

0.073

0.080

2

Total Fuel Cost per Unit

Rs./kWh

1.021

1.075

 

The non-tariff income is estimated at Rs.116.96 lakhs during the FY 2006-07 and is projected to be Rs.117.30 lakhs for the FY 2007-08. 

The sum of fixed and energy costs gives the total revenue requirement of the company for the FY 2005-06.  The revenue requirement less other income will be the revenue to be raised through tariff. This has been worked out in the Table 5 below

Table 5: Revenue Requirement

Particular

(Rs. crores)

Fixed Charges

302.18

Energy Charges   

158.90

Revenue Requirement

461.08

Other Income

1.17

Revenue to be raised through Tariff in FY 2007

459.91

The Petitioner has estimated a revenue requirement of Rs.459.95 crores after adjusting for its non-tariff income and derived the following fixed and energy components of tariff:

Table 6: Proposed Tariff Increase

Tariff Component

Rs./kWh

Fixed Charges Proposed

1.80

Energy Charges Proposed

1.075

Tariff Proposed

2.875

Existing Tariff

1.90

Increase in Tariff requested

0.975

The Petitioner requests the Honourable Commission to approve the estimated Rs.0.975/kWh increase in its tariff.

 

All Rights Reserved © 2007 'Tenughat Vidyut Nigam Limited' | Powered by : COMPUTER Ed.  |