Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Annual Revenue Requirement FY 2010-11


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 
2. Executive Summary

The Petitioner along with the information for FY’11, is also submitting the actual details of the operation during 2009-10 and requests Hon’ble Commission for truing the approved expenses based on actual expenses incurred by Petitioner.

Table 1: Generation Performance (MU)

 

2009-10

 

2010-11

 

Petition

Approved

Actual

Petition

Generation (MUs)

 

 

 

 

 

Unit –I

 

 

1345

 

1320

Unit-II

 

 

704

 

1435

Total

2490

2088

2049

 

2755

Station PLF (%)

67.68

56.75

55.68

 

74.88

Auxiliary Consumption

(%)

9.00

9.00

9.45

 

 

9.00

Heat Rate (kCal/kWh)

3100

2500

3418

 

3000

Gross Calorific Value of Coal

4300

4300

4300

 

4300

Specific Oil Consumption (kg/kWh)

2.5

2.0

3.296

 

2.5

 

 

 

 

 

 

With these parameters as base, the actual fixed costs for the year 2009-10 and projected costs for 2010-11 are summarized below:

Table 2: Summary of Fixed Costs (Rs.Crores)

 

2009-10

 

2010-11

 

Petition

Approved

Actual

Petition

Interest on Loan

83.15

83.06

 83.06

 

83.06

Depreciation

45.55

46.34

45.62

 

47.06

O&M Expenses

124.10

75.68

125.34

 

97.60

Interest on Working Capital

18.05

12.90

23.76

 

21.38

Return on Equity

19.43

21.82

19.99

 

23.73

Income Tax

-

-

-

 

-

Total

 

 

297.78

 

272.82

Petitioner would also like to state that the actual heat rate observed in 2009-10 was 3418 Kcal/kWh.
Petitioner is making all efforts to reduce the heat rate and has therefore targeted to achieve heat rate of 3000 Kcal/kWh for FY 11. Petitioner requests Hon’ble Commission to allow petitioner a higher heat rate than the approved value for 2009-10.

Petitioner would also like to state that the normative value of 2500 Kcal/kWh is applicable for plants coming after 1.4.2004 as per terms and conditions for determination of thermal generation tariff) regulations, 2004 notified by Hon’ble Commission.

For plants existing prior to 1.4.2004, which is applicable for the Petitioner the tariff order states “In case of existing generating stations the norms of operation shall be fixed based on past performance of the generating station and on efficiency improvement measures, as approved by the Commission.”
Petitioner would therefore request Commission to take cognizance of the past performance of the Petitioner, which is amongst one of the best in the region, and thus allow a higher heat rate.
In the mean while, Petitioner is also committed to bring down the heat rate from present values to 3000 Kcal/kWh.

In the last tariff order, Hon’ble Commission prescribed a cap on O&M as 2.5% of project cost at the time of CoD, where the project cost has been taken as Rs.1304.91 Cr. Petitioner would like to bring into notice of Hon;ble Commission that the notes in the Form 15 of the Thermal Generation tariff order states that the base O&M calculated as 2.5% of project cost at the time of CoD should be escalated at the rate of 10% to bring it to 1999-2000 level and escalation of 6% to be applied. Petitioner requests the Hon’ble Commission to kindly consider the base cost of O&M at the level of 1999-2000, for capping the O&M cost. An illustration of our understanding has been tabulated below.

Table 3: O&M for 2009-10

 

Calculation of O&M Costs

 

Particulars

 

Capital Cost at the time of COD year 1996-97

 

1304.91

 

2.5% of the Capital Cost

 

32.65

 

Escalating the cost to bring it to year 2000 level at the rate of 10%

 

43.42

 

Applying 6% escalation from year 2000 to 2010

 

77.76

 

O&M as per norms only on initial project cost for 2011

 

82.43

 

O&M approved including capitalization of 90.46 Cr and employee expense of 6.50 Cr for 2010

 

75.68

 

 

Petitioner would also like to submit that the O&M expenses as being observed are much higher than the normative value even by the above mentioned calculations and hence has initiated a diagnostic test for the same. With the information available as of now, Petitioner considers that inadvertently certain particulars which should have been under the head of capital expenditure, has been put in the O&M head resulting in a higher O&M expense in the past and also lower return to Petitioner severely impacting its financial position. This infirmity creeps into the system at the time any item is bought and not properly tagged. Petitioner is making all efforts to correct this at the earliest and has also considered the partial results of the actions already initiated in this petition, and thus has projected O&M at a lower value than made in the previous petition. In terms of percentage, Petitioner projects a reduction of approximately 22% from the actual O&M cost of 2009-10.

Petitioner had projected the delivered coal price to be Rs.1300 per MT for FY 10, whereas based on actual expenditure the delivered coal price observed was Rs.1343 per MT. This includes, transportation (including fuel for dozer), loss at 0.3%. Petitioner requests Commission to kindly consider the increased cost while truing the expenses for 2009-10.

The actual coal consumption (including transit loss of 0.3%) was 1547305 MT in FY 10, whereas Commission approved a consumption of 1207834 MT. As this is directly related to heat rate, Petitioner requests Commission to take a considerable view.

For FY ’11 Petitioner has assumed an increase of 10% on coal cost and hence has projected the delivered cost as 1477.70 per MT and a total consumption of 1934303 per MT.
Petitioner in FY ’10 observed oil price at Rs.38 086 per kL which is lower than the approved cost of Rs.39.045 per kL. For FY 11 oil price has been assumed to be at 43,269 per kL which is an increase of 13.6%. The oil prices have increased in recent times and thus the assumption made.
 

Table 4: Summary of Variable Costs (Rs.Crores)

 

2009-10

 

2010-11

 

Petition

Approved

Actual

Petition

Coal Cost

233.77

157.02

207.80

 

285.75

Oil Cost

24.32

16.30

25.72

 

29.80

Total Fuel Cost

258.09

173.32

233.52

 

315.56

 

 

The non-tariff income of Rs. 9.85 Crores was observed in FY 2011against an approved cost of Rs. 15.83 Crores and hence request Hon’ble Commission to kindly consider this as the non tariff income while truing the expenses.
The revenue requirement less other income will be the revenue to be raised through tariff. This has been worked out in the Table 5 below:
 

Table 5: Revenue Requirement (Rs. Crores)

 

2009-10

 

2010-11

 

Petition

Approved

Actual

Petition

Fixed Charges

290.28

239.80

297.78

 

272.82

Energy Charges 

258.08

173.32

233.52

 

315.55

Revenue Requirement

548.36

413.12

531.30

 

588.38

Other Income

2

15.43

9.85

 

10.97

Total

546.36

397.70

521.45

 

577.41

 

The Petitioner has estimated a revenue requirement of Rs 577.41 Crores after adjusting for its non-tariff income and derived the following fixed and energy components of tariff:

Table 6: Proposed Tariff Increase

 

2009-10

 

2010-11

 

Petition

Approved

Actual

Petition

Fixed Charges/unit

1.272

1.143

1.597

 

1.044

Energy Charges/unit

1.139

0.91

1.253

 

1.259

Tariff

2.411

2.053

2.85

 

2.303

 

The Petitioner requests the Honourable Commission to approve the estimated Rs. 0.25 per unit increase from the existing tariff of 2.053.

 

All Rights Reserved © 2010 'Tenughat Vidyut Nigam Limited' | Powered by : COMPUTER Ed.  |