FORM-9: Statement of Additional
Capitalization after COD
Name of the
Company: Tenughat Vidyut Nigam Limited
Name of the
Station: Tenughat Thermal Power Station
|
|
Year |
Work/Equipment |
Amount Capitalised/ |
Justification |
Admitted |
|
|
|
added afte previous
year COD |
Proposed to be |
|
cost |
|
|
|
(In Rs.) |
capitalized (In Rs.) |
|
|
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
|
1 |
2009-10 |
86837724.02 |
86837724.02 |
|
|
|
2 |
2010-11 |
533900000 |
266950000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
533,900,000 |
353,787,724 |
|
- |
1
In case the project has been
completed and any tariff notification(s) has already been issued
in the past by GOI, fill column 6 giving the cost as
admitted for the purpose of tariff notification already issued
by (Name of the authority) (Enclose copy of tariff order).
Note:
1. Fill the form in chronological
order.
2.
. In case initial spares are
purchased along with any equipment, then the cost of such spares
should be indicated separately, e.g. Rotor - 50 Crs
Initial spares - 5 Crs
|