Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Notice issued under section 64(2) of the Electricity Act 2003
2009-10


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 
1. Executive Summary

The Petitioner owns and operates an installed power generation capacity of 420 MW with two units of 210 MW each.  Historically the generating units have been operating at much below their potential because of transmission constraints and frequent tripping of transmission lines. In addition JSEB has not been in a position to consume the power generated when both the units operate and the station is asked to back down. However, in 2006-07, the plant has shown an impressive performance that can be attributed to both the units being able to dispatch simultaneously.

Table 1 provides the performance of the generating units during the period 2000-2007.

Table 1: Generation Performance (MU)

Year

Generation (MUs)

Total

Station PLF (%)

Auxiliary Consumption

(%)

Unit –I

Unit-II

2000-01

741

589

1330

36.11

16.09

2001-02

305

851

1156

31.39

15.79

2002-03

185

1183

1368

37.18

15.58

2003-04

616

731

1248

36.62

16.00

2004-05

1326

-

1326

36.04

17.60

2005-06

1240

289

1529

41.56

14.23

2006-07

1412

1303

2715

73.80

12.04

2007-08

226

1569

1795

48.68

9.95

2008-09

826

1397

2223

60.43

8.37

2009-10

1500

990

2490

67.68

9.00

Projected performance of the Petitioner (FY 2009-10):

Table 2: Generation Parameters for FY’10

Year

Generation (MU)

PLF (%)

Auxiliary Consumption (%)

Heat Rate (kCal/kWh)

Specific Coal Consumption (kg/kWh)

Specific Oil Consumption (kg/kWh)

2009-10

2490

67.68

9

3100

0.720

2.500

The fixed costs for the year 2009-10 are summarized below:

Table 3: Summary of Fixed Costs (Rs.Crores)

 

2009-10

Interest on Loan

83.15

Depreciation

45.55

O&M Expenses

124.09

Interest on Working Capital

18.04

Return on Equity

19.42

Income Tax

Nil

Total

290.28

The landed cost of coal for FY10 is projected to be Rs.1300.00/MT which is higher by Rs.5/MT only than last year. The cost of oil is expected to be at the same level as of last year i.e Rs.39045.20/KL respectively.

Table 4: Summary of Variable Costs (Rs.Crores)

S.No

Item

Unit

2008-09

(Actual)

2009-10

1

Coal Cost per Unit

Rs./kWh

1.014.

1.032

 

Oil Cost per Unit

Rs./kWh

0.1180.

0.107

2

Total Fuel Cost per Unit

Rs./kWh

1.132

1.139

 

The non-tariff income is projected to be at Rs. 200 Lakhs during the FY 10.The sum of fixed and energy costs gives the total revenue requirement of the company for the FY 2009-10. The revenue requirement less other income will be the revenue to be raised through tariff. This has been worked out in the Table 5 below:

Table 5: Revenue Requirement

Particular

(Rs. Lakhs)

Fixed Charges

29033.91

Energy Charges 

25807.74

Revenue Requirement

54835.58

Other Income

200

Revenue to be raised through Tariff in FY 2007

546365.58

The Petitioner has estimated a revenue requirement of Rs 546.37 Crores after adjusting for its non-tariff income and derived the following fixed and energy components of tariff:

Table 6: Proposed Tariff Increase

Tariff Component

Rs./kWh

Fixed Charges Proposed

1.272

Energy Charges Proposed

1.139

Tariff Proposed

2.411

Existing Tariff  as approved in 2007-08

2.05

Increase in Tariff requested

0. 361

The Petitioner requests the Honourable Commission to approve the estimated Rs. 0.36 per kWh increase in its tariff.

 

All Rights Reserved © 2010 'Tenughat Vidyut Nigam Limited' | Powered by : COMPUTER Ed.  |