FORM –1: Summary Sheet

Name of the Company: Tenughat Vidyut Nigam Limited

Name of the Station: Tenughat Thermal Power Station

Region: Eastern, State: Jharkhand, District: Ranchi

                      Rs.Lakhs

S.No.

Particulars

Actuals

Projected

 

 

2004-05

2005-06

2006-07

2007-08

2008-09

2009-10

1.1.

Depreciation (FORM-11)

4365.29

4368.96

4377.45

4388.05

4528

4551

1.2

Interest on Loan (FORM-12)

8319.51

8313.18

8564.93

8670.93

8305.68

8315.30

1.3

Return of Equity

1400

1400.00

1400.00

1400.00

1932.00

1943.00

1.4

Advance against Depreciation (FORM-13)

-

-

-

-

-

-

1.5

Interest on Working Capital(FORM-14)

1087.34

1015.16299

1687.39

1518.77

1562.91

1804.57

1.6

O & M Expenses (FORM-15)

5487.56

5816.82

6165.83

6535.78

8391.68

12409.83

 

Total

20659.70

20914.12

22195.60

22513.53

24188.27

29027.84

 

Less: Non Tariff Income

56.18

60.67

116.96

117.30

419

200

 

Fixed Charges to be recovered

20603.52

20853.45

22078.64

22396.23

23769.27

28827.84

 

 

 

 

 

 

 

 

2

Calculation Of  Rate of Energy  Charge (Rs./Kwh)1

1.128

2.55

1.02

1.08

1.139

1.139

2.1

Rate of Energy Charge from Primary Fuel(REC)P2

1.07

1.66

0.948

1.00

1.021

1.032

 

Net Energy Export (in MU)

1092.61

1529

2715

1679

2037

2266

2.2

Rate of Energy Charge from Secondary Fuel (REC)

0.058

0.89

0.073

0.080

0.118

0.107

2.3

Rate of Energy Charge ex-bus (REC) 3A, 3B, 3C

 

 

 

 

 

 

1. Details of calculations, considering equity as per regulations, to be furnished

2. If multi-fuel is used simultaneously, give 2.1 in respect of every fuel individually

3A. The rate of energy charges shall be computed for open cycle operation and combined cycle operation separately incase of gas/liquid fuel fired plants.

3B. The total energy charge shall be worked out based on ex-bus energy scheduled to be sent out in case of plants covered by ABT, and ex-bus energy delivered sent out in case of plants not covered by ABT as the case may be.

3C. Any escalation in fuel cost to be considered for subsequent years or FPA to take care of the escalation.