Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Notice issued under section 64(2) of the Electricity Act 2003
2008-09


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 

4. Fixed Charges

4.1 Capital Cost

The station comprises of 2 units of 210 MW each, the first unit was commissioned in September 1996 and the second unit in September 1997. The project cost as admitted by the petitioner in 2007-08 was Rs.1355.58 Crores. In the year 2008-09 assets worth Rs.0.24 Crores were capitalized during the year. An amount of Rs.0.12 Crores has been considered for this year, remaining amount would be considered in next year.(Details attached in depreciation schedule). Also, additional capitalization of Rs. 38.Crores on account of closing of contract with M/s BHEL has been done in this year hence in total an amount of Rs. 38.12 Crores has been capitalized during 2008-09.

The details of funding the project cost are given in Table 16 below:

Table 16: Project Cost

S.No.

Funding Source

Amount

(Rs. Crores)         

Phase 1: 2x210 MW

1

Project cost at the start of 2008-09

1355.58

2

Additional Capitalization in 2008-09

38.12

3

Total Project Cost

1393.70

5

Outstanding Debt Component at the start of 2008-09

638.90

6

Debt Component for additional capitalization

0.084

7

Total Debt

638.984

8

Equity Component at the start of 2008-09

100

9

Equity Component of additional capitalization

38.036

10

Total Equity

138.036

The majority of the Phase 1 of the project was financed by the State Government while about Rs.158 crores (11.67 % of the funding) was financed by PFC. The entire loan obtained from PFC has been repaid completely along with interest. The outstanding loan is from State Government only. The Petitioner has requested the State Government to reduce the interest rate in view of the lower interest rates provided by banks. Response from the State Government is still awaited.

The Petitioner is also planning to extend (Phase 2) the existing generating project, by adding three new units of 210 MW each, the capital cost of which for the FY 2007-08 is estimated to be Rs.354 crores. This is the Phase 2 of the generating project which will financed by a mix of debt in the form of funds from PFC and equity in the form of share capital contribution from Government of Jharkhand. It is expected to procure about Rs.284 crores from PFC and the remaining from the Government of Jharkhand. The decision on the expansion plan is expected early next year.


4.2 Elements of Fixed Costs

The fixed costs include:

  •  Interest on Loan

  • Depreciation

  • O&M Costs

  •  Interest on Working Capital

  • Return on Equity

  • Tax on Income

The details are submitted below for consideration of Honourable Commission

4.3 Interest on Loan

The loan outstanding as on 31.03.2009 is Rs.83.06 crores. As per the terms and conditions the State Government loan is repayable in 15 equal installments. But the Petitioner could not meet the repayment obligation due to insufficient funds on account of non-payment of electricity charges by the Jharkhand State Electricity Board (JSEB).

Table 17: Loan Outstanding and Interest Charges (Rs.Crores)

 

 

S.No

 

 

Name of the Institution

Balance at the beginning of the year

Loan received during the year

Repayment During the year

Balance O/S at the end of the year

Rate of Interest

%

Interest for the year

 

2005-06

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

-

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

19.00

-

49.00

13.25

6.49

 

Total 2005-06

638.90

19.00

-

657.90

 

85.65

 

2006-07

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

49.00

8.00

-

57.00

13.25

7.55

 

Total 2006-07

657.90

8.00

-

665.90

 

86.71

 

2007-08

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

 

 

30.00

13

3.9

 

Total 2007-08

638.90

 

 

638.90

 

83.06

 

2008-09

 

 

 

 

 

 

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

 

 

30.00

13

3.9

 

Total 2008-09

638.90

 

 

638.90

 

83.06

The Petitioner’s inability to repay loan is due to non-recovery of dues from JSEB. Therefore the Petitioner requests the Honourable Commission to approve the interest charges for 2008-09.

Table 18: Loan Outstanding and Interest Charges for 2008-09 (Rs.Crores)

 

 

S.No

 

 

Name of the Institution

Balance at the beginning of the year

Loan received during the year

Repayment During the year

Balance O/S at the end of the year

Rate of Interest

%

Interest for the year

1

Bihar Govt. Loan

608.90

 

-

608.90

13

79.16

2

Jharkhand Govt. Loan

30.00

-

-

30.00

13

3.9

 

Total 2008-09

657.90

-

-

665.90

 

83.06


4.4 Depreciation

The Petitioner has calculated the depreciation on its fixed assets on historical capital cost of the asset. Depreciation is calculated annually as per the straight line method as per rates of depreciation prescribed in the schedule attached at Appendix-II of the JSERC (Terms and Conditions for Determination of Thermal Generation Tariff) Regulations, 2004, and depreciation cost has been arrived at accordingly.

Table 19a: Depreciation for the Plant (Rs. Crores)

S.No

Asset Classification

Asset value at the beginning of 2008-09

Rate of depreciation (%)

Depreciation

Amount (Rs.Cr.)

1

Land

38.64

-

-

                Buildings

 

 

 

1

Factory Buildings

42.10

3.60

1.52

2

Residential Buildings

22.82

1.80

0.41

3

Non Residential Buildings

17.61

1.80

0.32

               Roads

 

 

 

1

Pucca Roads

17.77

1.80

0.32

2

Boundary Wall & Others

2.23

1.80

0.04

               Plant and Machinery

 

 

 

1

Plant & Machinery

1072.32

3.60

38.60

2

D.G. Set

2.16

6.00

0.13

3

Refrigeration

0.02

6.00

0.001

4

Internal Wiring

0.00

6.00

0.00

5

Overhead line

48.91

3.60

1.76

6

Hydraulic works

79.24

1.80

1.43

7

Tools and Tackles

0.41

3.60

1.48

8

Miscellaneous Equipment

0.09

6.00

0.005

9

Air Conditioners

0.33

18.00

0.06

10

Dozers

2.82

18.00

0.51

11

Computers

0.27

6.00

0.02

12

Furniture and Fixtures

0.46

6.00

0.03

13

Office equipment

0.16

6.00

0.01

Total

1207.19

 

45.16

As per the JSERC regulations, the residual life of an asset is considered as 10% and depreciation is allowed upto a maximum of 90% of the historical capital cost of the asset. Therefore, depreciation is not calculated on the assets where the cumulative depreciation has reached 90% of the historical cost of such assets.

Table 19 b : Depreciation  for Head Office (Rs. Crores)

S.No

Asset Classification

Asset value at the beginning of 2008-09

Rate of depreciation (%)

Depreciation

Amount (Rs.Cr.)

1.   

Furniture & Fixtures

0.39

6.00

0.02

2.   

Close Circuit Camera

0.06

6.00

0.0035

3.   

Photocopy Machine

0.04

6.00

0.0023

4.   

Refrigerator

0.064

6.00

0.004

5.   

Miscellaneous Equipment

0.06

6.00

0.0035

6.   

Telephone & Mobile Sets

0.076

6.00

0.0046

7.   

EPBX System

0.06

6.00

0.0034

8.   

Fax Machine

0.006

6.00

0.0004

9.   

Typewriter

0.005

6.00

0.0003

10.      

Television

0.001

6.00

0.0011

11.      

Computer & Accessories

0.16

6.00

0.0097

12.      

Generator

0.025

6.00

0.0015

13.      

Air Conditioner & Coolers

0.17

18.00

0.03

14.      

Car

0.14

18.00

0.026

15.      

Cycle

0.00

6.00

0.00

16.      

V.Set

0.005

6.00

0.00

17.      

Capital Work in Progress

0.52

-

-

Total

1.74

 

0.11

 

Table 19 c : Depreciation on Additional Capitalization (Rs. Crores)

S.No

Asset Classification

Asset value at the beginning of 2008-09

Rate of depreciation (%)

Depreciation

Amount (Rs.Cr.)

1.   

Plant & Machinery

0.00

0.00

0.00

2.   

New EPABX

0.00

0.00

0.00

3.   

New Dozer

0.00

0.00

0.00

4.   

Air Compressor for TH

0.00

0.00

0.00

5.   

New Engine for Dozer

0.00

0.00

0.00

6.   

Pay Loader

0.00

0.00

0.00

7.   

Electronic Weigh Bridge

0.04

0.00

0.00

8.   

Airconditioner

0.01

0.00

0.00

9.   

Air Compressor for CHP

0.00

0.00

0.00

10.      

Lift

0.00

0.00

0.00

11.      

High Mast towers

0.00

0.00

0.00

12.      

Furniture & Fixtures

0.09

0.01

0.01

13.      

Computer & other office equip

0.02

0.00

0.00

14.      

Office Equipment

0.08

0.00

0.00

15.      

Land

0.00

0.00

0.00

16.      

Ambassdor car/Jeep

0.00

0.00

0.00

17.      

Mobile Sets

0.00

0.00

0.00

18.      

Tools & Tackles

0.00

0.00

0.00

19.      

Miscellaneous Equipment

0.00

0.00

0.00

20.      

V-Sat

0.00

0.00

0.00

Total

0.24

 

0.02

 

Table 19: Total Depreciation
 

S.No

Item

Depreciation

Amount (Rs.Cr.)

1.      

Deprectaion for Plant

45.17

2.      

Depreciation for HO

0.11

3.      

Depreciation for Additional Capitalization

0.00

Total

45.28

It is requested that the Honourable Commission may kindly approve the depreciation at Rs. 45.28 crores for the year 2008-09.
 

4.5 Operation and Maintenance (O&M) Expenses

The O&M expenses include expenditure incurred in the operation and maintenance of the generating station, including employee cost, repairs and maintenance, consumption of stores and spares, water charges, ash disposal, pollution control cess, insurance and other administrative and general expenses of the Petitioner corporate office at Ranchi. The maintenance expenditure has increased substantially due to the age of the plant and numerous outages experienced. In the previous tariff order for FY 2007-08 the Honourable Commission had approved the normative O&M expenses as per the JSERC (Terms and Conditions for Determination of Thermal Generation Tariff) Regulations, 2004 for plants set prior to 01.04.2004 that is 2.5% of the capital cost escalated at 6% per annum from the year of commissioning and also an amount of Rs.9.23 crores on account of overhaul of unit 1.  This year due to higher R&M costs the petitioner has incurred expense on account of O&M of Rs.84.12 Crores.

Table 20: O&M Expenses

Item

 (Rs. Crores)

Employee Cost

15.32

A&G Expenses

10.59

R&M

11.26

O&M including Capital Expenditure

46.85

Total

84.12


The major components of the O&M expenses have been explained below:

a) Employee cost: The actual employee cost for FY 2007-08 was Rs.13.27 crores The employee cost increases continuously on account of inflation, increment in salaries and wages, honorarium/incentives and increased demand for trained manpower on account of increased development in infrastructure sectors. For the year 2008-09 the employee cost is at Rs. 15.12 Crores. Additional Rs. 20 Lakhs has been made on the account of Fringe Benefit Tax on the necessary employee expenses. This has been added in the employee cost hence total employee cost is Rs.15.32 Crores

b) Repairs and Maintenance (R&M): The Petitioner has to carry out regular repairs and maintenance of its generating plant to ensure maximum generation by optimum utilization of generating assets. The Petitioner undertakes preventive maintenance activities for all critical assets in addition to breakdown maintenance. The actual R&M costs in the year 2007-08 are Rs.4.30 crores. The Petitioner requests the Honourable Commission to approve Rs.11.25 crores for FY 2008-09 inclusive of R&M expenditure and other maintenance expenditures to keep its plant running. This is on account of civil works in the non-residential buildings and power house road and drains.

c) Administrative and General (A&G) Expenses: A&G expenditure represents cost of general administration such as rent, rates, taxes, legal expenses, professional fees, conveyance and traveling expenses, printing and stationery, bank charges, etc. In the year 2007-08 A&G expenses was Rs.6.88 Crores. For the FY 08-09 the Petitioner has incurred an expense of Rs.10.58 Crores

d) O&M Expenses: The petitioner has incurred an amount of Rs. 8.98 Crores on account of Annual Maintenance Contract and Other Operation and Maintenance  Contract.

e) Capital Maintenance: The Petitioner had incurred Rs. 86.82 crores towards capital maintenance during the last 5 years period, that is 2002-03 to 2006-07, including towards spares. These charges are being treated as deferred revenue expenses and proposed to be charged to revenue account in 5 annual installments. The year wise details of capital maintenance expenses and the amounts proposed to be charged to revenue account are detailed in the table below:

 Table 21: Year wise Capital Maintenance Expenditure (Rs. Lakhs)

 

Year

Amount

Proposed to be charged to Revenue in 5 annual installments

 

 

2002-03

2003-04

2004-05

2005-06

2006-07

2007-08

2008-09

2002-03

886.45

177.29

177.29

177.29

177.29

177.29

 

 

2003-04

45.46

-

9.09

9.09

9.09

9.09

9.09

 

2004-05

1209.48

-

-

241.90

241.90

241.90

241.90

241.9

2005-06

3267.00

-

-

-

653.40

653.40

653.40

653.4

2006-07

2856.29

-

-

-

-

571.26

571.26

571.26

2007-08

5519.20

-

-

-

-

-

1103.84

1103.84

2008-09

6134.86

 

 

 

 

 

 

1226.97

Total

 

177.29

186.39

428.28

1081.68

1652.94

2579.49

3797.37

The amount proposed to be charged during 2008-09 is Rs.37.97 crores.

Interest on Working Capital:

In accordance with clause (v) of Regulation 21 of the JSERC (Terms and Conditions for Determination of Thermal Generation Tariff) Regulations, 2004, working capital in case of coal based fired generation stations shall cover:

  • Cost of coal for 1½ months for pithead generating stations and 2 months for non-pithead generating stations, corresponding to the target availability

  • One month stock of secondary fuel oil

  • O&M expenses for 1 month

  • Maintenance spares @ 1% of plant and equipment cost as on 01.04.2004 or the date of commercial operation, whichever is later; and

  • Receivables equivalent to 2 months of fixed and variable charges for sale of    electricity calculated on target availability

The interest on working capital is estimated at Rs.15.75 crores for the year 2008-09 as detailed in the Table 22 below:

Table 22: Interest on Working Capital (Rs. Lakhs)

S.No

Particulars

2008-09

 

1

Cost of Coal for 1½ months

2582.21

2

Secondary Fuel Oil for 1 month

201.08

3

Operation & Maintenance Expenses for 1 month

701.01

4

Maintenance Spares @ 1% of Plant and Equipment

1172

5

Receivables Equivalent to 2 Months of Fixed and Variable Charges

7899.82

6

Total Working Capital

12556.12

7

Interest on Working Capital @ 12.5%

1569.51


Return on Equity

For the last so many years, the Petitioner has been asking return on its initial equity contribution of Rs.100 Crores. The petitioner had also not asked any return on the additional capitalization during these years.

In the year 2007-08 the petitioner made the contract settlement and paid Rs.38 Crores to M/s BHEL Limited. This amount was a part of project cost but as this was not settled, the petitioner in the larger interest of consumer did not include the amount in project cost.

Petitioner has closed this contract and paid the required amount and hence now request Hon’ble Commission to admit this cost. Also Petitioner would like to request the Hon’ble Commission to treat the total amount as equity contribution as complete payment has been made through its reserves and also no return or interest has been charged earlier. Petitioner would also like to draw the point that its equity contribution is much lower than the capped percentage of 30% as investments made through its reserves has not been added in equity component.

Petitioner has also capitalized assets worth Rs. 0.24 Crores during the year, of which Rs.0.12 Crores has been capitalized in this year. Applying normative debt equity ratio of 70:30, an additional equity contribution of Rs. 0.036 Crores has been considered. The total equity contribution is Rs.138.036 Crores. Petitioner requests Hon’ble Commission to kindly approve the return of Rs.19.32 Crores as Return on equity for the FY 2008-09.

Table 23: Return on Equity (Rs.Crores)

Particular

Proposed for 2008-09 (Rs.Crores)

Equity

138.036

Return on Equity (%)

14%

Return on Equity

19.32


Income Tax

There is no assessable income for Income tax purpose and hence no tax on income is proposed for the year 2008-09.

Elements of Fixed Costs

The fixed costs for the year 2008-09 are summarized below:

Table 24: Summary of Fixed Costs (Rs.Crores)

Particular

2008-09

Interest on Loan

83.06

Depreciation

45.28

O&M Expenses

84.12

Interest on Working Capital

15.70

Return on Equity

19.32

Income Tax

-

Total

247.48

The proposed fixed charges of Rs.247.48Crores and expected net generation of 2037 MUs the Petitioner requests the Honourable Commission to kindly approve this.

 

All Rights Reserved © 2010 'Tenughat Vidyut Nigam Limited' | Powered by : COMPUTER Ed.  |