| 1.
Executive Summary The Petitioner owns and operates an installed
power generation capacity of 420 MW with two units of 210 MW
each. Historically the generating units have been operating at
much below their potential because of transmission constraints
and frequent tripping of transmission lines. However, after
2006-07, the plant has shown an impressive performance and now
both the units are able to dispatch simultaneously.
Table 1 provides the performance of the
generating units during the period 2000-2009.
Table 1: Generation Performance (MU)
|
Year |
Generation (MUs) |
Total |
Station
PLF (%) |
Auxiliary Consumption
(%) |
|
Unit –I |
Unit-II |
|
2000-01 |
741 |
589 |
1330 |
36.11 |
16.09 |
|
2001-02 |
305 |
851 |
1156 |
31.39 |
15.79 |
|
2002-03 |
185 |
1183 |
1368 |
37.18 |
15.58 |
|
2003-04 |
616 |
731 |
1248 |
36.62 |
16.00 |
|
2004-05 |
1326 |
- |
1326 |
36.04 |
17.60 |
|
2005-06 |
1240 |
289 |
1529 |
41.56 |
14.23 |
|
2006-07 |
1412 |
1303 |
2715 |
73.80 |
12.04 |
|
2007-08 |
226 |
1569 |
1795 |
48.68 |
9.95 |
|
2008-09 |
826 |
1397 |
2223 |
60.43 |
8.37 |
|
|
Last year’s
performance of the Petitioner (FY 2008-09):
Table 2: Generation Parameters
for FY’09
|
Year |
Generation (MU) |
PLF (%) |
Auxiliary Consumption (%) |
Heat
Rate (kCal/kWh) |
Specific Coal Consumption (kg/kWh) |
Specific Oil Consumption (kg/kWh) |
|
2008-09 |
2223 |
60.43 |
8.37 |
3075 |
0.715 |
2.779 |
|
|
The fixed costs for the year 2008-09
are summarized below:
Table 3: Summary of Fixed Costs (Rs.Crores)
|
|
2008-09 |
|
Interest on Loan |
83.05 |
|
Depreciation |
45.28 |
|
O&M Expenses |
84.12 |
|
Interest on Working Capital |
15.70 |
|
Return on Equity |
19.32 |
|
Income Tax |
Nil |
|
Total |
247.48 |
|
The landed cost of
coal and oil for FY08-09 was Rs.1295.50/MT and Rs.39045.20/KL
respectively.
Table 4:
Summary of Variable Costs (Rs.Crores)
|
S.No |
Item |
Unit |
2007-08
(Approved) |
2007-08
(Actuals) |
2008-09
(Actual) |
|
1 |
Coal Cost per Unit |
Rs./kWh |
0.82 |
0.926 |
1.014. |
|
|
Oil Cost per Unit |
Rs./kWh |
0.06 |
0.108 |
0.1180. |
|
2 |
Total Fuel Cost per
Unit |
Rs./kWh |
0.88 |
1.034 |
1.132 |
|
Data taken from
the letter of GM TTPS
The non-tariff income was Rs. 419.5 lakhs during the FY 2008-09
The sum of fixed
and energy costs gives the total revenue requirement of the
company for the FY 2008-09. The revenue requirement less other
income will be the revenue to be raised through tariff. This has
been worked out in the Table 5 below:
Table 5: Revenue Requirement
|
Particular |
(Rs. crores) |
|
Fixed Charges |
247.48 |
|
Energy Charges |
230.70 |
|
Revenue Requirement |
478.18 |
|
Other Income |
4.195 |
|
Revenue to be raised through Tariff in FY 2009 |
473.98 |
|
The Petitioner has
estimated a revenue requirement of Rs 473.98 Crores after
adjusting for its non-tariff income and derived the following
fixed and energy components of tariff:
Table 6: Proposed Tariff Increase
|
Tariff Component |
Rs./kWh |
|
Fixed Charges Proposed |
1.194 |
|
Energy Charges Proposed |
1.132 |
|
Tariff Proposed |
2.327 |
|
Existing Tariff |
2.05 |
|
Increase in Tariff requested |
0.277 |
|
The Petitioner
requests the Honourable Commission to approve the estimated Rs.
0.28 per kWh increase in its tariff. |