Home Performance Recruitment Organization Resources Scoreboard Environment Activities Contact Us

Tenders | Notices

Public Notice : Notice issued under section 64(2) of the Electricity Act 2003
2008-09


Download :Tariff Petition
'PDF Format'
Download Acrobat Reader

 
1. Executive Summary

The Petitioner owns and operates an installed power generation capacity of 420 MW with two units of 210 MW each.  Historically the generating units have been operating at much below their potential because of transmission constraints and frequent tripping of transmission lines. However, after 2006-07, the plant has shown an impressive performance and now both the units are able to dispatch simultaneously.

Table 1 provides the performance of the generating units during the period 2000-2009.

Table 1: Generation Performance (MU)

Year

Generation (MUs)

Total

Station PLF (%)

Auxiliary Consumption

(%)

Unit –I

Unit-II

2000-01

741

589

1330

36.11

16.09

2001-02

305

851

1156

31.39

15.79

2002-03

185

1183

1368

37.18

15.58

2003-04

616

731

1248

36.62

16.00

2004-05

1326

-

1326

36.04

17.60

2005-06

1240

289

1529

41.56

14.23

2006-07

1412

1303

2715

73.80

12.04

2007-08

226

1569

1795

48.68

9.95

2008-09

826

1397

2223

60.43

8.37

Last year’s performance of the Petitioner (FY 2008-09):

Table 2: Generation Parameters for FY’09

Year

Generation (MU)

PLF (%)

Auxiliary Consumption (%)

Heat Rate (kCal/kWh)

Specific Coal Consumption (kg/kWh)

Specific Oil Consumption (kg/kWh)

2008-09

2223

60.43

8.37

3075

0.715

2.779

The fixed costs for the year 2008-09 are summarized below:

Table 3: Summary of Fixed Costs (Rs.Crores)

 

2008-09

Interest on Loan

83.05

Depreciation

45.28

O&M Expenses

84.12

Interest on Working Capital

15.70

Return on Equity

19.32

Income Tax

Nil

Total

247.48

The landed cost of coal and oil for FY08-09 was Rs.1295.50/MT and Rs.39045.20/KL respectively.

Table 4: Summary of Variable Costs (Rs.Crores)

S.No

Item

Unit

2007-08 (Approved)

2007-08

(Actuals)

2008-09

(Actual)

1

Coal Cost per Unit

Rs./kWh

0.82

0.926

1.014.

 

Oil Cost per Unit

Rs./kWh

0.06

0.108

0.1180.

2

Total Fuel Cost per Unit

Rs./kWh

0.88

1.034

1.132

 

Data taken from the letter of GM TTPS

The non-tariff income was Rs. 419.5 lakhs during the FY 2008-09

The sum of fixed and energy costs gives the total revenue requirement of the company for the FY 2008-09. The revenue requirement less other income will be the revenue to be raised through tariff. This has been worked out in the Table 5 below:

Table 5: Revenue Requirement

Particular

(Rs. crores)

Fixed Charges

247.48

Energy Charges   

230.70

Revenue Requirement

478.18

Other Income

4.195

Revenue to be raised through Tariff in FY 2009

473.98

The Petitioner has estimated a revenue requirement of Rs 473.98 Crores after adjusting for its non-tariff income and derived the following fixed and energy components of tariff:

Table 6: Proposed Tariff Increase

Tariff Component

Rs./kWh

Fixed Charges Proposed

1.194

Energy Charges Proposed

1.132

Tariff Proposed

2.327

Existing Tariff

2.05

Increase in Tariff requested

0.277

The Petitioner requests the Honourable Commission to approve the estimated Rs. 0.28 per kWh increase in its tariff.

 

All Rights Reserved © 2010 'Tenughat Vidyut Nigam Limited' | Powered by : COMPUTER Ed.  |